YardMath

How much concrete for a 10×10 slab

A 10 × 10 ft slab is the usual shed pad or small patio, and it sits right on the line between mixing bags yourself and ordering a truck. The sheet below is prefilled with 10 × 10 ft at 4 in thick and a 10 % allowance for uneven ground; it prints the cubic yards, the bag count at the manufacturer’s yields, and both prices. Change the thickness to 5–6 in if a vehicle will park on it.

For this example1.36 cu ydconcrete to order, 10 % extra, about $465 in bagged.The sheet below is filled in for it; change any figure to your own.

Form 28 · Materials estimateFigures checked 2026-09-04
US customary
Shape
Quantity · Amount
  1. 01Slab volume10 × 10 ft × 4 in33.3 cu ft
  2. 02Concrete to order, 10 % extra36.7 cu ft1.36 cu yd
  3. 03Weight, cured150 lb per cu ft2.76 tons
  4. 04Ready-mix$160 per cu yd, ordered by the quarter yard1.5 cu yd$240
  5. 0580 lb bags0.6 cu ft per bag (manufacturer yield) at $862 bags$465
Total, bagged$465
  • 62 bags is a lot of mixing; a ready-mix truck would be about $217.
  • Order ready-mix by the quarter yard, rounded up; the truck cannot deliver a fraction of what you order back.
Buy as
Ready-mix is priced per cubic yard delivered

How thick

Four inches is the standard for a shed, patio, walkway or hot tub pad on compacted ground. A driveway, a garage floor or anywhere a vehicle parks wants 5–6 in and steel in it. Thickness is the dimension people shave to save bags, and it is the one that decides whether the slab cracks: concrete is strong in compression and weak in bending, and a thin slab bends.

01020304thick4 inlength × width
  1. 01Subgrade, compacted
  2. 02Gravel base, 4 in, compacted
  3. 03Slab at the finished thickness, mesh or rebar on chairs at mid-depth
  4. 04Forms, squared and braced; the measurement is inside them

Forms, base and reinforcement

Dig to the slab thickness plus 4 in for the base. Build the forms from 2×4 or 2×6 lumber staked every 2–3 ft on the outside, top edge at the finished height. Check square with the 3-4-5 rule: measure 3 ft along one side and 4 ft along the other from a corner; the diagonal between the marks is 5 ft when the corner is square. The two diagonals of the whole form match on a rectangle.

Spread 4 in of crushed stone inside the forms and compact it. The base drains water away and gives even support; pouring straight on clay is the usual cause of a slab that heaves and cracks. Lay a vapor barrier on top if the slab will be a floor. Set wire mesh or #3 rebar on chairs so it sits in the middle of the slab, not on the base where it does nothing.

Bags or ready-mix

Under about half a cubic yard, bags and a rented mixer are practical for two people. A 10 × 10 at 4 in is more than a yard, and the sheet counts the bags at the manufacturer’s yield (an 80 lb bag makes 0.60 cu ft). Mixing that many by hand takes most of a day, the first bags are setting before the last are poured, and the slab ends up with cold joints.

A ready-mix truck delivers the whole slab in one pour. Plants sell by the cubic yard, rounded up to the quarter yard, and most charge a short-load fee under their minimum, often 5–10 yards; the sheet rounds the same way and tells you when bags would be cheaper. The truck needs to get within a chute’s reach of the forms, about 15 ft, and it is heavy enough to crack a thin existing driveway. If it can’t get close, you wheelbarrow: a 6 cu ft barrow carries 4–5 cu ft of wet concrete, so a yard is six or seven loads.

Measuring and ordering

  1. Measure the inside of the forms, not the outside; the form lumber takes 1½ in on each side.
  2. Type length, width and thickness, and keep the 10 % allowance: the base is never perfectly flat.
  3. Pick the bag size you can lift; the sheet counts bags for whichever you choose.
  4. Compare the bagged total with the ready-mix line, then edit the ready-mix price to your plant’s quote, including any short-load fee.
  5. Order ready-mix in quarter-yard steps, rounded up, for the morning, with forms, base, mesh and two people ready before the truck arrives.

Pouring and curing

Pour, spread with a rake, and screed with a straight 2×4 across the forms. Float it, wait for the bleed water to leave, then trowel or broom. Cut a control joint down the middle within a day, about a quarter of the slab depth, so the crack that will come goes where you put it. Keep the slab damp for a week: mist it, cover it with plastic, or spray curing compound; concrete that dries in the sun never reaches its strength. Keep foot traffic off for a day and vehicles off for a week.

Common mistakes

  • No compacted base. The slab settles unevenly and cracks along the soft spot.
  • Thin edges. They take the most load; keep the full thickness to the form.
  • Under-ordering. A truck that comes back with a quarter yard costs another delivery fee and gives you a cold joint.
  • Mesh on the ground. Reinforcement lifted into the slab works; lying on the gravel it is decoration.
  • Letting it dry fast. A slab that goes pale in an afternoon is losing water it needed for curing.

Open the concrete calculator with these numbers

Questions people ask

How many bags of concrete for a 10×10 slab?
The sheet counts them for the thickness and bag size you pick, at the manufacturer’s yields (80 lb makes 0.60 cu ft, 60 lb 0.45 cu ft). At 4 in it is a lot of bags; the note under the sheet says when a truck would be less work.
Is a 10×10 slab too small for a ready-mix truck?
No, but it is below most plants’ minimum, so expect a short-load fee. Get the quote with the fee included and put that figure in the ready-mix price field.
Do I need rebar in a 4 in slab?
For a shed or patio, wire mesh or #3 rebar on 18–24 in centers keeps cracks from opening. A slab that carries a vehicle should be 5–6 in with rebar.
How long before I can build on it?
Walk on it after a day, frame on it after 3–7 days, and expect most of the design strength at 28 days.